You are here

    Home » Sec. 18.1-6. Alternative Policies on Protests of Award or Decisions to Award a Contract in Lieu of Va. Code S 2.2-4360 through S 2.2-4362 and Va. Code S 2.2-4364

    Sec. 18.1-6. Alternative Policies on Protests of Award or Decisions to Award a Contract in Lieu of Va. Code S 2.2-4360 through S 2.2-4362 and Va. Code S 2.2-4364

     

    Sec. 18.1-6. Alternative policies on protests of award or decisions to award a contract in lieu of Va. code § 2.2-4360 through § 2.2-4362 and Va. code § 2.2-4364.
     
    (a) The following are the exclusive procedures for a bidder or offeror to protest the city's award or decision to award a contract.
     
    (1) Any protest to award a contract shall be in writing and shall be delivered so that it is received by the city manager not later than five (5) business days after announcement of the award or decision to award, whichever comes first. Otherwise any such protest shall be deemed to be waived.
     
    (2) Except for a protest of an emergency or sole source procurement, a protest of a city award or decision to award a contract may only be made by a person who submitted a bid or proposal for the procurement at issue and who was reasonably likely to have its proposal accepted but for the city's decision. In the case of an emergency or sole source procurement, a protest may only be made by a person who can show that he was reasonably likely to have submitted a successful bid or proposal if the procurement had been other than emergency or sole source.
     
    (3) Protests shall only be granted if (1) the protester has complied fully with this Sec. 18.1-6 and there has been a violation of law, the Lynchburg public procurement code, or mandatory terms of the solicitation that clearly prejudiced the protestor in a material way, or (2) a statute requires voiding of the decision.
     
    (4) The city manager shall issue a written decision on a protest within ten (10) days of its receipt by the city manager.
     
    (5) If the protest is denied, the protestor may only appeal the denial or otherwise contest or challenge the procurement by then filing suit in the Lynchburg circuit court, Lynchburg, Virginia, and serving the city with such suit within ten (10) days of such denial. Otherwise, the city manager's decision shall be final and conclusive, and the protester's right to appeal the denial or to otherwise contest or challenge the procurement shall be deemed to be waived.
     
    (6) The city should defer award of a contract where the decision to award has been protested unless there is a written determination by the city manager that proceeding without delay is necessary to protect the public interest or unless the bid or offer of the prospective awardee would expire.
     
    (7) The validity of a contract awarded and accepted in good faith shall not be affected by the fact that a protest or appeal is filed.
     
    (8) The exclusive relief allowed if a protest is granted is to void the decision being protested. If a contract has already been awarded and performance under the contract has begun, the contract need not be voided if not in the public interest to do so. Under no circumstances will any monetary amount be allowed to the protestor as part of any relief granted.
     
    (9) Strictly following these procedures shall be a mandatory prerequisite for protest of the city's award or decision to award a contract. Failure by a bidder to follow these procedures strictly shall preclude that bidder's protest and be deemed to constitute a waiver of any protest.
     
    (b) A protest may not be based upon the alleged non-responsibility of a person to whom the city awards or makes a decision to award a contract. (Ord. of 12-13-05, Ord. No. O-05-161)
     
    Last updated date: 10/23/2006 4:15:21 PM