    Fifth St Phase II

    The Fifth Street Phase II project encompasses streetscaping and a utility project that covers waterline, stormline and sanitary sewer lines along with improvements to the sidewalks, curbs & gutter and handicapped ramps.  The project will include restoring the nostalgic bricks back into the old neighborhood look and feel.  There will be several tree plantings to soften the hardscape. This project will also add additional parking areas to businesses along the Fifth Street Corridor. 

    The existing utilities in this area are over 100 years old, which is a large part of the reason for the improvements. 

    The project limits are from Harrison Street to Main Street along the Fifth Street corridor and is expected to last until June 2013.

     

    City of Lynchburg Representatives
    Project Manager Lee Newland 434-455-3947
    Construction Coordinator Edd Wood 434-455-4446
    General Contractor Counts & Dobyns 434-821-2774
    Consultant/Engineer Wiley/Wilson 434-947-1901

     

    Construction Timeline
    Design Phase January - March 2011
    Bid April - May 2011
    Construction September 2011 - July 2013
    Project Close Out August - September 2013

     

     

    Current Posted Projects
    2012 Bridge Maintenance Project Lower Bluff Walk Phases II & III
    Bridge Safety Inspections Main Street Bridge Rehabilitation
    Fifth Street Phase II McConville Rd Culvert
    Jefferson Street South / Lower Bluffwalk Phase I Rivermont Avenue Bridge
    Kemper Street Bridge Wards Road Bridge Improvements
    Lakeside Dr / Park Ave / Memorial Ave Intersection  

     

     "Working Together to Serve You Better!"

     

    No votes yet